Advice on operation: Evaluation


In this section

This section describes the following evaluation scenarios:

  • Incorrect date and time in the result file

  • Evaluation procedure aborts


Incorrect date and time in the result file

Scenario

Solution

The result file shows incorrect date and time.

The date and time recorded in the result file are taken from the PC system clock settings.

Action: Check the system clock settings.


Evaluation procedure aborts

Scenario

Solution

The evaluation procedure aborts.

Instructions in an evaluation procedure refer to curves by identification number irrespective of the curve names. Make sure that the curves processed when the procedure is executed are compatible with those processed when it was recorded. An evaluation procedure aborts if you try to store resulting curves at the position of an original raw data curve.


2005-06-15